Activities are the basic building blocks of the Process Flow tool. This topic will
explain some important concepts about adding and connecting activities to your process
flows. This topic will also explain different methods for adding and connecting
activities.
About Connectors and Stacked Blocks
One of the important things to understand are the similarities and differences between
connectors and stacked blocks. A connector is a connection between two activities,
as shown in the following image:
During a simulation run, tokens will use connectors to go from one activity to the next
downstream activity. Some activities allow more than one outgoing connector, but many do
not.
A stacked block is a set of activities that have been snapped together into one
movable block, as shown in the following image:
Stacked blocks let you easily link a set of activities into a single sequence of steps,
making it easy to move and edit them as if they were one block. When activities are linked
together in a stacked block, they are automatically connected as though each activity were
connected with connectors. In other words, these two process flows will function
identically:
You can create stacked blocks through the object library as explained in
Adding Activities from the Process Flow Library or you can drag an
activity above or below another activity to snap them together.
Number of Outgoing Connectors
Most activities can only have one outgoing connection because they usually implement a
very simple piece of logic on a token. In that case, the activity can simply send the token
to the next downstream activity when that logic is complete. However, a few activities can
have more than one outgoing connection. For example, a Decide activity can have more than
one outgoing connection because tokens might need to be sent to a different downstream
activity based on certain changing conditions. To check whether an activity allows more than
one connection, read the reference page for the specific activity you're interested in.
You will need to understand how connectors work for activities that can have more than
one outgoing connector. The following list explains a few important concepts to keep in
mind:
Each outgoing connection has a number (also sometimes called
a rank) based on the order in which you created them. When you create
an outgoing connection from one activity to another activity, this connection will
automatically be assigned a number (rank). For example, the first outgoing connection
you create will be assigned a rank of 1, the second will have a rank of 2, and so forth.
You may have noticed that this is similar to how port connections work between objects
in the 3D simulation model.
The token will be sent to the next activity based on the
number assigned to the outgoing connector. The underlying logic of the activity
depends on the numbers (ranks) of the outgoing connectors. For example, if you wanted to
send 75% of tokens to the activity connected to the first outgoing connector, you would
send them to connector 1. If you wanted to send 25% to the activity connected to the
second outgoing connector, you would send them to connector 2.
You can re-rank outgoing connectors or assign names to
connectors if needed. You can edit the activity's properties to change the
ranks of the outgoing connectors or assign a name to a connector. You can also assign a
name to a connector for easier reference if needed. (See Changing the
Rank Number or Name of Outgoing Connectors for more information.) Activities that
allow for more than one outgoing connector will usually have a group of properties
labeled Connectors Out that can be used to manage the outgoing connectors.
NOTE: If you need to refer to a connector's name in a command of some sort, make sure
you put it in quotation marks (" ") so that the FlexSim system can recognize it as a
string.
Adding Activities from the Process Flow Library
There are several ways to add activities to a process flow. One way is to add an activity
from the Process Flow Library:
Make sure that the left pane is open to the Library tab (not the Toolbox tab).
Click somewhere inside a process flow to make the process flow view active. The
Library will change to show the process flow activities (instead of the standard FlexSim
objects).
Drag an activity from the Library into the process flow.
If you drop an activity from the library onto another activity within the process flow
view, the activities will be joined together by adding the new activity to the end of the
block. Dropping an activity in between two activities in a block will insert the dropped
activity in between the two activities.
You can also add activities from the library and immediately connect it to a stacked
block:
Drag an activity from the Library into the process flow without releasing the mouse
button.
While holding down the mouse button, drag the activity on top of another activity or
stacked block and release the mouse. The activity will be appended to the end of the
stacked block.
You can also add and connect activities using the Quick Library, which is a condensed
menu of the process flow activities, as shown in the following image:
If you want to add an activity to a blank area using the Quick Library inside a process
flow:
Double-click in the process flow to open the Quick Library.
Click the icon for the activity you want to add.
If you want to add an activity to the end of a stacked block using the Quick Library:
Point your mouse on the bottom edge of an activity or stacked block. The mouse icon
will change to a chain link.
Double-click the edge to open the Quick Library again.
Click the icon for the activity you want to add. The activity will be appended to
the end of the stacked block.
The Process Flow tool has two methods for inserting an activity into a stacked block, as
explained in the following sections.
Adding an Activity from the Process Flow Library
To add an activity inside a stacked block from the Library:
Drag an activity from the Process Flow library to any area of the process flow.
While pressing the mouse button, drag the activity into a stacked block to any
position in the stacked block. Release the mouse button when it is in its desired
position.
Using the Quick Library
To add an activity inside a stacked block using the Quick Library:
Point your mouse to the line between two activities until the line turns yellow, as
shown in the following image:
Double-click the line to open the Quick Library again.
Click the icon for the activity you want to add. The activity will be inserted in
the middle of the stacked block.
Moving and Deleting an Activity From a Stacked Block
To move and/or delete an activity from a stacked block:
Press and hold the Ctrl key. Click the activity you want to move and drag it to a
different position in the stacked block. If you want to delete the activity, drag it
away from the stacked block to another space in the process flow.
With the activity still selected, press the Delete key to delete it.
Copying and Pasting Activities or Stacked Blocks
You can easily copy an activity or stacked block. When you copy and paste an activity or
stacked block, it will automatically retain all the same settings from the original activity
or stacked block. You can also copy activities or stacked blocks from one process flow to
another in the same simulation model.
To copy an activity or stacked block:
Click the activity or stacked block to select it.
Use Ctrl+C to copy the activity.
Use Ctrl+V to paste the copied activity.
Images copied from other applications can also be pasted directly into ProcessFlows.
Adding Outgoing Connectors
If you want to create an outgoing connector from one activity to another:
Point your mouse on the bottom edge of an activity or block. The mouse icon will
change to a chain link.
Click the edge of the activity or block and, while holding down the mouse, drag the
mouse toward the activity you want to connect. You'll notice a connector coming from the
edge of the block to the mouse pointer.
Release the mouse when it is connected to the activity. You can change the curvature
or position of the connector by clicking on it and manipulating its curve handles if
needed.
You can also add a new activity to the end of a connector using the Quick Library:
Point your mouse on the bottom edge of an activity or block. The mouse icon will
change to a chain link.
Click the edge of the block and, while holding down the mouse, drag it a little bit
toward the bottom of the screen. You'll notice a connector coming from the edge of the
block to the mouse pointer.
When you release the mouse, the Quick Library will appear.
Click the icon for the activity you want to add. The activity will be appended to
the end of the stacked block, as shown in the following animated image:
Removing Connectors and Separating Stacked Blocks
To remove a connector:
Click the connector. It will turn yellow to indicate it is highlighted.
Press the Delete key. The connector will disappear.
To separate activities in a stacked block:
Click anywhere inside the stacked block to select it. Its borders will turn yellow
to indicate it is selected. You will also notice that some scissor icons will appear to
the left in between the activities, as shown in the following image:
Click the scissors icon between the two activities you want to separate. The stacked
block will separate into two different blocks.
Changing the Rank Number or Name of Outgoing Connectors
Certain types of process flow logic might depend on connector rank numbers or names. By
default, each outgoing connector is assigned a rank number according to the order in which
the outgoing connectors were created. This section will cover changing ranks, adding names,
and other related topics.
Viewing Rank Numbers
To view the rank numbers:
Click an activity to select it.
If the activity has more than one outgoing connector, the rank number will be
displayed next to the connector.
Changing Rank Numbers
To change a rank number of an outgoing connector:
Double-click the connector.
In Quick Properties, use the arrows next to the From
Rank or To Rank boxes to increase or reduce its
rank numbers.
Adding Connector Names
To change a name of an outgoing connector:
Double-click the connector.
In Quick Properties in the Name box, type an
appropriate name for the connector.
The new name will now be displayed in the Process Flow. You can adjust the font and font
size in Quick Properties as well.
Deleting Connector Names